Everything in order before the ‘Solinso installation’ begins

A successful installation doesn’t start on the roof — it starts the day before. Find out what every installer and installation company needs to check before the first panel hook is fitted.

FREE: Solinso Pre-installation checklist

Print directly or save to your phone — ready for use on the job.
solinso checklist rgba
4
Sections

Safety, Roof, Materials & String current

20+
Checkpoints

Fully in line with the Solinso installation instructions.

1
Page A4

Print-ready, including a signature line

100%
FREE

Available to download immediately, no registration required

Safety — non-negotiable

Working on a roof remains one of the most hazardous working environments in the installation sector. It is therefore no coincidence that the safety section of the checklist is listed first. Ensure that the following points are in place before anyone goes up onto the roof:

Please note

A fall protection harness that has not been inspected regularly may not provide adequate protection. Always check the inspection date before use.

Roof inspection — to measure is to know

Many installation errors stem from a roof that has not been properly prepared. The Mystiek has specific requirements for the substructure. Before starting, check:

Tip for installation companies

Have the roof inspection and cable preparation carried out by a separate technician the day before the installation. This saves an average of 45–90 minutes on the day of the installation itself, and prevents a whole team from having to wait around for a solution.

Equipment required — never drive the same route twice

A shortage of materials is the most common cause of delays on the day of installation. The checklist includes a comprehensive list of materials specifically for the installation of Solinso solar roof tiles. 

Please ensure you have the following:

Mounting materials

Tools

For installation companies

Consider putting together a dedicated “Solinso toolkit” for each installation: a box or bag containing all the consumables in the correct quantities. This reduces packing time and minimises the risk of errors when listing materials.

Checking string current— always measure

After connecting each string, the voltage must be measured and recorded using a multimeter. This is a mandatory step prior to connecting to the inverter. The checklist provides space for three strings, including a field for noting the measured values in volts.

An abnormal reading may indicate a loose connector, a damaged panel or an error in the cable labelling. By identifying this immediately on site, you can avoid a fault report after completion.

Using the checklist

The PDF has been designed for both digital use (on a tablet or phone on the roof) and as a printed A4 document. The checklist concludes with a signature line for the installer and a box for the client to tick — useful as a handover document or for record-keeping.

For installation companies, the checklist is also suitable for use as part of a project file or as an appendix to the work order.

Solinso-checklist

Download the checklist for free

Print directly or save to your phone — ready for use on the job.

Read more

Preview Image article

TOPCon or IBC: current solar cell technology

October 22, 2026
When comparing solar panels or solar roof tiles, people often look at peak wattage and price. But it is what lies beneath – the solar cell – that determines how much of the sunlight is ultimately converted into electricity. Two technologies are currently...
Preview Image article

The impact of roof design on esthetics

September 29, 2026
Why the appearance of your solar roof is just as important as the energy it generates When homeowners consider solar panels, their focus is almost always on efficiency: how many watts peak, how much they’ll save, and how long it will take to recoup the...
Preview Image article

Energy storage: the solution for a stable grid

August 22, 2026
The missing link in the energy transition Solar panels have been a huge success. They are appearing on more and more roofs, and on sunny days the Netherlands sometimes generates more green electricity than the grid can handle. Yet this success has also become...
Solinso-gdpr
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.